• Lietuvių
    • English
  • Lietuvių 
    • Lietuvių
    • English
  • Prisijungti
Peržiūrėti įrašą 
  •   DSpace pagrindinis
  • Mokslinės publikacijos (PDB) / Scientific publications (PDB)
  • Moksliniai ir apžvalginiai straipsniai / Research and Review Articles
  • Straipsniai Web of Science ir/ar Scopus referuojamuose leidiniuose / Articles in Web of Science and/or Scopus indexed sources
  • Peržiūrėti įrašą
  •   DSpace pagrindinis
  • Mokslinės publikacijos (PDB) / Scientific publications (PDB)
  • Moksliniai ir apžvalginiai straipsniai / Research and Review Articles
  • Straipsniai Web of Science ir/ar Scopus referuojamuose leidiniuose / Articles in Web of Science and/or Scopus indexed sources
  • Peržiūrėti įrašą
JavaScript is disabled for your browser. Some features of this site may not work without it.

A new analytical methodology to handle time-cost trade-off problem with considering quality loss cost under interval-valued fuzzy uncertainty

Thumbnail
Peržiūrėti/Atidaryti
8422-Article Text-19847-2-10-20190221 (003).pdf (394.6Kb)
Data
2019
Autorius
Haghighi, Mohammad Hossein
Mousavi, Seyed Meysam
Antuchevičienė, Jurgita
Mohagheghi, Vahid
Metaduomenys
Rodyti detalų aprašą
Santrauka
This paper proposes a new framework in addressing time-cost trade-off problem (TCTP) under uncertainty. First critical path analysis is carried out based on developing a new intervalvalued fuzzy (IVF)-program evaluation and review technique (PERT) approach. Then, non-conformance risks that influence on execution quality of activities are identified and evaluated based on a new approach that considers probability of risk along with impacts on time, cost, and performance. Then, a new mathematical model under IVF uncertainty is presented to decrease project total time while considering time, cost and quality loss cost that is determined in form of rework or modification cost. Finally, the approach categorizes the activities in three groups based on their level of criticality. Outcome of this methodology is a scheduling that addresses time, cost and quality trade-offs in addition to categorizing activities in different groups based on being on the critical path. Therefore, the project manager not only gets a scheduling based on the TCTP with considering quality loss cost but also has a knowledge of activities that require extra attentions. To show the steps of this methodology, an existing application from the literature is adopted and solved.
Paskelbimo data (metai)
2019
URI
https://etalpykla.vilniustech.lt/handle/123456789/124559
Kolekcijos
  • Straipsniai Web of Science ir/ar Scopus referuojamuose leidiniuose / Articles in Web of Science and/or Scopus indexed sources [7946]

 

 

Naršyti

Visame DSpaceRinkiniai ir kolekcijosPagal išleidimo datąAutoriaiAntraštėsTemos / Reikšminiai žodžiai InstitucijaFakultetasKatedra / institutasTipasŠaltinisLeidėjasTipas (PDB/ETD)Mokslo sritisStudijų kryptisVILNIUS TECH mokslinių tyrimų prioritetinės kryptys ir tematikosLietuvos sumanios specializacijosŠi kolekcijaPagal išleidimo datąAutoriaiAntraštėsTemos / Reikšminiai žodžiai InstitucijaFakultetasKatedra / institutasTipasŠaltinisLeidėjasTipas (PDB/ETD)Mokslo sritisStudijų kryptisVILNIUS TECH mokslinių tyrimų prioritetinės kryptys ir tematikosLietuvos sumanios specializacijos

Asmeninė paskyra

PrisijungtiRegistruotis