• Lietuvių
    • English
  • English 
    • Lietuvių
    • English
  • Login
View Item 
  •   DSpace Home
  • Mokslinės publikacijos (PDB) / Scientific publications (PDB)
  • Moksliniai ir apžvalginiai straipsniai / Research and Review Articles
  • Straipsniai Web of Science ir/ar Scopus referuojamuose leidiniuose / Articles in Web of Science and/or Scopus indexed sources
  • View Item
  •   DSpace Home
  • Mokslinės publikacijos (PDB) / Scientific publications (PDB)
  • Moksliniai ir apžvalginiai straipsniai / Research and Review Articles
  • Straipsniai Web of Science ir/ar Scopus referuojamuose leidiniuose / Articles in Web of Science and/or Scopus indexed sources
  • View Item
JavaScript is disabled for your browser. Some features of this site may not work without it.

Combining Monte Carlo simulation and Bayesian networks methods for assessing completion time of projects under risk

Thumbnail
View/Open
Combining Monte Carlo Simulation and Bayesian.pdf (2.208Mb)
Date
2019
Author
Namazian, Ali
Yakhchali, Siamak Haji
Yousefi, Vahidreza
Tamošaitienė, Jolanta
Metadata
Show full item record
Abstract
In this study, Monte Carlo simulation and Bayesian network methods are combined to present a structure for assessing the aggregated impact of risks on the completion time of a construction project. Construction projects often encounter different risks which affect and prevent their desired completion at the predicted time and budget. The probability of construction project success is increased in the case of controlling influential risks. On the other hand, interactions among risks lead to the increase of aggregated impact of risks. This fact requires paying attention to assessment and management of project aggregated risk before and during the implementation phase. The developed structure of this article considers the interactions among risks to provide an indicator for estimating the effects of risks, so that the shortage of extant models including the lack of attention to estimate the aggregated impact caused by risks and the intensifying impacts can be evaluated. Moreover, the introduced structure is implemented in an industrial case study in order to validate the model, cover the functional aspect of the problem, and explain the procedure of structure implementation in detail.
Issue date (year)
2019
URI
https://etalpykla.vilniustech.lt/handle/123456789/148525
Collections
  • Straipsniai Web of Science ir/ar Scopus referuojamuose leidiniuose / Articles in Web of Science and/or Scopus indexed sources [7946]

 

 

Browse

All of DSpaceCommunities & CollectionsBy Issue DateAuthorsTitlesSubjects / KeywordsInstitutionFacultyDepartment / InstituteTypeSourcePublisherType (PDB/ETD)Research fieldStudy directionVILNIUS TECH research priorities and topicsLithuanian intelligent specializationThis CollectionBy Issue DateAuthorsTitlesSubjects / KeywordsInstitutionFacultyDepartment / InstituteTypeSourcePublisherType (PDB/ETD)Research fieldStudy directionVILNIUS TECH research priorities and topicsLithuanian intelligent specialization

My Account

LoginRegister