• Lietuvių
    • English
  • Lietuvių 
    • Lietuvių
    • English
  • Prisijungti
Peržiūrėti įrašą 
  •   DSpace pagrindinis
  • Mokslinės publikacijos (PDB) / Scientific publications (PDB)
  • Moksliniai ir apžvalginiai straipsniai / Research and Review Articles
  • Straipsniai Web of Science ir/ar Scopus referuojamuose leidiniuose / Articles in Web of Science and/or Scopus indexed sources
  • Peržiūrėti įrašą
  •   DSpace pagrindinis
  • Mokslinės publikacijos (PDB) / Scientific publications (PDB)
  • Moksliniai ir apžvalginiai straipsniai / Research and Review Articles
  • Straipsniai Web of Science ir/ar Scopus referuojamuose leidiniuose / Articles in Web of Science and/or Scopus indexed sources
  • Peržiūrėti įrašą
JavaScript is disabled for your browser. Some features of this site may not work without it.

Application of hybrid SWARA–BIM in reducing reworks of building construction projects from the perspective of time

Thumbnail
Peržiūrėti/Atidaryti
sustainability-12-08927.pdf (1.564Mb)
Application of Hybrid SWARA?BIM in Reducing Reworks of Building Construction Projects from the Perspective of Time.pdf (18.59Mb)
Data
2020
Autorius
Khalesi, Hamidreza
Balali, Amirhossein
Valipour, Alireza
Antuchevičienė, Jurgita
Migilinskas, Darius
Zigmund, Viačeslav
Metaduomenys
Rodyti detalų aprašą
Santrauka
One of the major issues of the construction industry has been the “reworks” that affect the time, quality, and cost of projects. Therefore, reworks and the ineffective use of site resources and materials will always result in significant losses on projects. The development of information technology has led to the widespread use of Building Information Modelling (BIM) to enhance the delivery of more sustainable building construction projects. The purpose of this study is to combine the Step-wise Weight Assessment Ratio Analysis (SWARA) method and BIM technologies to identify and reduce time delays caused by reworks in construction projects. Firstly, 49 rework causes in residential buildings were identified and ranked. Then, BIM was generated and compared to the initial model. It was observed that working hours were reduced by 4.6%. Moreover, using an Earned Value Management (EVM) system, a 0.06 increase in Schedule Performance Index (SPI) factor was illustrated. Results obtained by this study provide an effective step in reducing a project’s time in the construction industry
Paskelbimo data (metai)
2020
URI
https://etalpykla.vilniustech.lt/handle/123456789/150863
Kolekcijos
  • Straipsniai Web of Science ir/ar Scopus referuojamuose leidiniuose / Articles in Web of Science and/or Scopus indexed sources [7946]

 

 

Naršyti

Visame DSpaceRinkiniai ir kolekcijosPagal išleidimo datąAutoriaiAntraštėsTemos / Reikšminiai žodžiai InstitucijaFakultetasKatedra / institutasTipasŠaltinisLeidėjasTipas (PDB/ETD)Mokslo sritisStudijų kryptisVILNIUS TECH mokslinių tyrimų prioritetinės kryptys ir tematikosLietuvos sumanios specializacijosŠi kolekcijaPagal išleidimo datąAutoriaiAntraštėsTemos / Reikšminiai žodžiai InstitucijaFakultetasKatedra / institutasTipasŠaltinisLeidėjasTipas (PDB/ETD)Mokslo sritisStudijų kryptisVILNIUS TECH mokslinių tyrimų prioritetinės kryptys ir tematikosLietuvos sumanios specializacijos

Asmeninė paskyra

PrisijungtiRegistruotis