dc.contributor.authorTomczak, Michał
dc.contributor.authorJaśkowski, Piotr
dc.date.accessioned2025-03-18T07:32:35Z
dc.date.available2025-03-18T07:32:35Z
dc.date.issued2019
dc.identifier.issnN/Aen_US
dc.identifier.urihttps://etalpykla.vilniustech.lt/handle/123456789/156904
dc.description.abstractIn carrying out construction projects, enterprises strive to obtain the highest degree of harmonization of the work of the resources involved. It is manifested in ensuring continuous and regular production with a full usage of their executive potential. The purpose of harmonization is to eliminate unjustified interruptions in the work of resources. When planning the realization of non-repetitive construction projects, one should use methods of scheduling that allow the analysis of the project model not only as a function of time. It is also important to take into account the effectiveness of using your own resources and limitations in their availability. The article analyzes the problem of harmonizing the work of crews of the general contractor, performing non-rhythmic, non-cyclical and inhomogeneous processes under the assumption of deterministic operating conditions. An important issue from the point of view of reducing the costs of crews’ employment is the continuity of their work. A mathematical model was developed concerning the problem of minimization of downtime in the work of the general contractor crews with a directively fixed time and limit of the project realization cost, taking into account the limitations in the availability of crews and the possibility to outsource works to subcontractors. The possibility of subcontracting works does not allow for a clear indication in the project model sequences of processes carried out by crews and the usage of previously developed scheduling methods. The method of solving the model (in a linear form with continuous and binary variables) is presented in the example. Additionally, the proposed method allows analyzing the impact of the amount of downtime at work on the duration of the project and the impact of the work outsourced to subcontractors on the continuity of the general contractor’s work.en_US
dc.format.extent8 p.en_US
dc.format.mediumTekstas / Texten_US
dc.language.isoenen_US
dc.relation.urihttps://etalpykla.vilniustech.lt/handle/123456789/156029en_US
dc.rightsAttribution 4.0 International*
dc.rights.urihttp://creativecommons.org/licenses/by/4.0/*
dc.subjectconstruction project managementen_US
dc.subjectproject schedulingen_US
dc.subjectrenewable resource utilizationen_US
dc.subjectschedule optimizationen_US
dc.subjectsubcontractors’ selectionen_US
dc.titleThe method of scheduling construction projects increasing the use of resources of the general contractoren_US
dc.typeKonferencijos publikacija / Conference paperen_US
dcterms.accessRightsLaisvai prieinamas / Openly availableen_US
dcterms.accrualMethodRankinis pateikimas / Manual submissionen_US
dcterms.alternativeTechniquesen_US
dcterms.issued2019-05-17
dcterms.licenseCC BYen_US
dcterms.references24en_US
dc.description.versionTaip / Yesen_US
dc.contributor.institutionLublin University of Technologyen_US
dcterms.sourcetitleInternational Conference Modern Building Materials, Structures and Techniques (MBMST 2019)en_US
dc.identifier.eisbn9786094761973en_US
dc.identifier.eissn2029-9915en_US
dc.publisher.nameVilnius Gediminas Technical Universityen_US
dc.publisher.nameVilniaus Gedimino technikos universitetasen_US
dc.publisher.countryLithuaniaen_US
dc.publisher.countryLietuvaen_US
dc.publisher.cityVilniusen_US
dc.description.fundingorganizationPolish Ministry of Science and Higher Educationen_US
dc.description.grantnumberS/63/2019en_US
dc.identifier.doihttps://doi.org/10.3846/mbmst.2019.019en_US


Files in this item

Thumbnail
Thumbnail

This item appears in the following Collection(s)

Show simple item record

Kūrybinių bendrijų licencija / Creative Commons licence
Except where otherwise noted, this item's license is described as Kūrybinių bendrijų licencija / Creative Commons licence